We would like to reschedule the previously announced maintenance window on the i3D.net aggregation switches of Suite 24 in the SmartDC Rotterdam datacenter. We will perform firmware upgrades to address known defects and upgrade network capacity to facilitate traffic growth.

Maintenance window:
Wednesday the 30th of May, 2018, from 02:00 to 06:00 CET (01:00 to 05:00 UTC)

Planned Actions:
- We will upgrade the firmware to the latest patch release of Brocade's target path software branch.
- We will upgrade network capacity to facilitate traffic growth.
- We will upgrade top-of-rack switch firmware where relevant.

Estimated impact:
During the window, each aggregation switch in the fabric will be reloaded on a sequential basis and racks directly connected to that specific device will experience around 15 minutes of downtime while we wait for its uplink to recover. We expect to perform most of the top-of-rack switch reloads during this same window, but might take a bit longer due to the number of racks involved.